| Owner |
State Railway of Thailand |
| |
|
| Main contractor |
Sinothai Public Company Limited. |
| |
|
| Problem |
The airport rail link project has
been designed to support customers and passengers
between Suwannabhumi Airport and the city center.
The initial project was designed by the Hopewell
group and used double elevated line. The structures
of this project start from Makasan up to Rama
IX, which is more than 2,500 meters.
This project had been changed to a new line concept
and the existing construction can not be used.
|
| |
|
| |
|
| |
|
| Our solutions |
We had to demolish all the existing
construction (elevated beams, supports, columns...).
To accomplish this work, high technology and important
safety procedure have been taken. The cut of large
pieces of reinforced concrete was made by WIRE SAW.
And they were moved away by over 250 TONS cranes.
During the construction period, more than 350 cuts
or 58,000 tons of existing structures have to be
done within 3 months.
The demolishing work had to be done on top of
railway in use, so all safety was provided in
this project.
REENTECH also participates in the new construction
project going up to Suvarnabhumi Airport.
REENTECH has supplied CHEMICAL BOLTS, to anchor
the re-bar of the rail support and also the station.
From the Suvarnabhumi Airport to Rama IX, there
were more than 180.000 pairs.
|